EXP-07 · Build·Drawing set rev. 0
Hemp Landmarks
People visit places, not statistics. Three sheets that turn the record into buildings people can walk into: one landmark per country, a lab that wires some of them with sensors, and the moonshot of a whole city block. Each one feeds the next.
00The set
Three sheets, one ladder
Every figure carries a label: sourced (opened and read), verify (from a summary), sample (made up to show the design), or unknown (the number does not exist yet).
A landmark per country
A public hemp building in each country, documented and filmed. Case one is the Marseille school whose hempcrete lot went out three times.
Phase 1 to 2 · first story in 2027
Living buildings lab
Sensors and core samples in hemp walls, measuring moisture, carbonation and decay: the permanence data the carbon registries say they lack.
Phase 2 · first dataset before Verra's Q3 2027 reassessment
A hemp city block
A neighbourhood built with hemp, every wall on the Hemp Clock. The showcase for bio-based building, and the proof the first two worked.
Phases 3 to 4 · a moonshot, not a plan yet
LSheet series L · Culture
A landmark per country
Hempin's record already holds the hard part: public buyers who wrote “béton de chanvre” into a tender. A landmark turns one of those notices into a place with a door, a film and a plaque. One flagship per country, chosen by evidence, never by who pays.
L-1Run a building through the five tests
→Where it stands
A public notice names hemp. Found by the tender feed.
Award notice and a site visit confirm the walls exist.
The wall record reaches Documented. The building appears on the Hemp Clock.
Owner consents, film made, plaque on the wall.
It stops at Built.
Missing: The wall record, Owner consent, Honest story.
Mix decides whether the carbon claim is true: a cement-heavy mix still emitted 8.16 kg CO2/m² Sourced
L-1What makes a building a landmark
| Test | What passes | Evidence tier needed | Why it is there |
|---|---|---|---|
| Public door | A school, library, station, sports hall or civic building anyone can visit, at least on open days | Declared | People visit places. A private villa cannot carry a national story. |
| Hemp in the envelope | Hempcrete walls, hemp insulation or hemp boards as a named part of the build, not a sample panel | Documented (a tender lot, spec or invoice) | Ties the building to the Construire en Chanvre and RE2020 world the corridor runs in. |
| The wall record | Binder, mix, density, wall thickness, m² laid, applicator, hurd origin | Documented for all, Verified for at least the mix | Mix decides whether the carbon claim is true: a cement-heavy mix still emitted 8.16 kg CO2/m² Sourced |
| Owner consent | The public owner agrees to filming, a plaque and a public page | Documented (signed letter) | No landmark is published about a building without its owner. |
| Honest story | The page says what is known, what is not, and what a relaunched tender does and does not prove | Reviewed against the Evidence Ledger | A landmark built on a hyped number would cost more trust than it earns. |
L-2The candidate register
◎Selected
FR · case one
SOLEAM Marseille · École des Arts, lot 3 hempcrete facades
Step 1 · tender seen. A notice names hemp. Next: read the award notice and visit the site, so the walls can be confirmed.
This is case one: the lot went out three times. Its draft page is below.
Candidates by country
L-2The four steps every candidate walks
Tender seen
A public notice names hemp. Found by the tender feed.
Built
Award notice and a site visit confirm the walls exist.
Recorded
The wall record reaches Documented. The building appears on the Hemp Clock.
Landmark
Owner consents, film made, plaque on the wall.
L-3Landmark page · draft
FR · Candidate 01
A school in Marseille, three calls for hemp
A public body asked for hempcrete facades and did not get a usable answer. Twice. This is the story of what it takes to get the walls built.
✎Notes on the page
- The headline is the market failing in public. "Went out three times" is sourced from Hempin's positioning work Sourced. A déclaration d'infructueux under the Code de la commande publique means no bids, or bids that were irregular or over budget. It never says no supplier exists.
- One fact is not yet joined. The relaunched school and the SOLEAM "École des Arts" lot in the TED buyer list may be the same project. Nobody has confirmed it. Before this page goes live, someone reads the notices and joins or splits them Unknown
- Empty fields stay visibly empty. The page fills in as the wall record reaches each tier, so a visitor sees the building become documented over time.
- The timeline extends past the tender. Award, walls up, recorded, filmed: the arc from a failed call to a finished wall.
- Two actions only. Visit, which sends people to the place, and Ask BUD, which answers "what is hempcrete and why did this tender struggle" with sources.
L-4The film: three minutes, one wall
The tender. A scroll through the real notice: lot 3, béton de chanvre. Then the word infructueux.
L-5The plaque on the wall
Hemp landmark · France · 01
These walls are made of hemp and lime.
Stored in this facade
— t CO2
Range, method and source: scan
—Why the line stays a dash
Cast lime or a hemp board, sized for a school entrance. The stored-carbon line stays a dash until the Stored Carbon Ledger holds a range with a method behind it. When it does, the plaque shows the range, never a single proud number.
The code opens the landmark page, which opens the wall record, which opens the passports of the hurd. A visitor can walk from the door to the field.
The pattern drawn here is a placeholder, not a working code.
L-6What this sheet cannot claim
- That any candidate building exists. The register holds tenders, not buildings.
- That a relaunched tender proves missing supply. It proves the market did not clear in public.
- A stored-carbon number for any landmark. The up-to-16 kg CO2/m² figure is the best case in one study, not a default to multiply Sourced
- That a country with no candidate has no hemp building. It means Hempin's record has none.
BSheet series B · Science
Living buildings lab
The gap the registries named is permanence: does the carbon in a hemp wall stay there? The lab instruments one new wall from the day it is cast and takes cores from walls already 5, 10 and 20 years old. It publishes data, never a credit.
B-1Site 1 · the new wall
Cast with sensors inside
A corridor building under construction. Sensors must go in while the hempcrete is placed; they cannot be added to a finished wall without drilling. This is why the lab rides on the corridor's tenders.
Gives: Drying curve, moisture by depth, day-one baseline.
B-1Site 2 · the old walls
Cores from aged buildings
Three or more existing hemp buildings of known age and known mix. Small cores are taken, tested for carbonation depth and carbonate content, then patched.
Gives: The carbonation curve over decades, months before the new wall can.
B-1Site 3 · the test panels
Reference panels outdoors
Panels cast from two or three recorded mixes, including a cement-heavy one, exposed side by side and sampled on a schedule.
Gives: A controlled comparison, and destructive tests without harming a building.
B-2Wall section with sensor positions
◉S4 · at stud face
A hemp wall's real failure mode is the frame: if moisture stays high at the stud, decay starts there first.
The section colours each depth by the nearest sensor's reading at that month: a cast wall starts wet, dries from the outside in, and the stud dries last.
B-4The lab dashboard, one wall · corridor building A, wall N-02
B-1Borrowing time from old walls
√tTry a coefficient
No lab can measure 35 years in nine months. Cores from walls that are 5, 10 and 20 years old give an early curve now, while the new wall's sensors start the long record that confirms or corrects it.
Depth is not mass: the carbonate content of each core slice turns a depth into tonnes.
B-3What is measured, how, and what it cannot tell
| Quantity | Method | Cadence | Answers | Limit |
|---|---|---|---|---|
| RH and temperature in the wall | Embedded sensors S1 to S4, logged | Every 15 min | Is the wall drying, and does moisture sit at the stud? | Sensors drift and fail; each is calibrated before casting and checked yearly. |
| Indoor and outdoor climate | Loggers W1, W2 | Every 15 min | What the wall was exposed to, so results transfer to other climates | One climate per site; the network needs sites in several countries. |
| Carbonation depth | Core, split, sprayed with a pH indicator; the carbonated zone stays colourless | New wall: 3, 6, 12 months, then yearly. Old walls: once | How far the lime has turned back into carbonate | Shows depth, not mass. Needs the next row to become tonnes. |
| Carbonate content | Lab analysis of core slices (for example thermogravimetric) | Same as cores | How much CO2 the binder has taken up, by depth | Lab cost per sample is unknown until quoted. |
| Decay and mould | Visual and borescope inspection at the core port and stud; timber moisture content | Twice a year | Is the stored carbon in the hemp and timber staying put? | Early years will show little. That absence is still data. |
| The wall record | Mix, binder, density, thickness, m², applicator, hurd passport | Once, at casting | Makes every reading comparable and links it to the Stored Carbon Ledger | Old walls may lack a full record; those cores carry a lower tier. |
B-5The open record each reading lands in
lab_reading {
site: "corridor-A / wall N-02"
wall_record: → Stored Carbon Ledger entry
sensor: "S4 · stud face · cal 2027-02-11"
quantity: "relative_humidity"
value: 71.2
unit: "%"
method: "protocol v0.3 §4.2"
taken_at: 2027-09-18T06:15Z
tier: "verified"
dataset_doi: → Zenodo, released quarterly
}B-5Why it is shaped this way
Every reading names its wall, its sensor's calibration date and the protocol version. Datasets are released quarterly with a DOI, so a researcher can cite the exact snapshot.
The record lives beside the Stored Carbon Ledger, not inside it. The Ledger holds the cited storage range per building; the lab holds the measurements that one day tighten that range.
B-6Nine months to Q3 2027
CSheet series C · Moonshot
A hemp city block
A whole block where hemp is the ordinary way to build: a school, homes, a library, a workshop, a square. Every wall on the Hemp Clock, every sensor feeding the open lab, any wall scannable. A vision board, not a project yet.
C-1Site plan
▣A · School
The first building a city will ask for: public door, daily use, the class kit next door.
Timber frame, hempcrete cast around it, lime finishes.
A wall joins the block counter only when its record reaches Documented, and the number shown is always a range: low and high, with the method behind each end.
C-2Block counter · sketch
— t CO2
Stored in the walls of this block, as a range with its method. The block's counter is the Hemp Clock zoomed into one neighbourhood.
The square holds the public display: the block's range beside the national and world clocks, so a visitor sees their street as part of something larger.
C-2Every wall on the Hemp Clock
| Building | Walls recorded | Tier | Range |
|---|---|---|---|
| A · School | 0 / — | — | — |
| B · Library | 0 / — | — | — |
| C1, C2 · Homes | 0 / — | — | — |
| D · Workshop | 0 / — | — | — |
C-3What must be true before the block is a plan
Landmarks exist
At least five countries with a recorded landmark, so the block is a sequel, not a gamble.
Measured by Sheet L's register reaching step 4.
The lab has a curve
Published carbonation and moisture data from old and new walls, cited by someone outside Hempin.
Measured by Sheet B's datasets and their citations.
The corridor clears volume
A region can supply hurd and applicators for a block without starving its other tenders.
Measured by The Grand Est corridor's cleared tonnes.
A city wants it
A municipality or developer with a site, a planning route and its own reasons. Hempin documents and connects; it does not develop property.
Measured by A letter of intent on the record.
C-4Numbers that do not exist yet
- Tonnes of hurd a block needs. Depends on the design and the wall thickness Unknown
- Stored carbon for the block. Needs mixes and areas Unknown
- Cost compared with a conventional block. Outside this set: the lab states no money figures.
- How long hempcrete keeps its carbon over 35 years and beyond. That is what Sheet B exists to find out Unknown
SSources
Where the figures come from
§Sources and how this set connects
- Carbon Leadership Forum, Arehart et al. 2020: hempcrete walls store up to 16 kg CO2/m² net of production; a 425 kg/m³ cement-heavy mix still emitted 8.16 kg CO2/m² Sourced
- Verra, hemp cultivation methodology: on hold since December 2023, reassessment Q3 2027 Sourced
- EU CRCF, Delegated Act 2026/285: 35-year minimum for carbon storage in products Sourced
- Hempin positioning work: the Marseille school lot that went out three times, and what infructueux does and does not mean Sourced
- Hempin tender scan: public hempcrete buyers in TED notices 2024 to 2026, used for the candidate register Sourced
- Sensor methods are standard building-physics and concrete-carbonation practice; the protocol itself is for a research partner to set Open question
Related experiments: the Grand Est corridor supplies Site 1 and Gate 3; the Hemp Clock receives every wall record.